Project Name: IMPROVING DRINKING WATER SUPPLY OF THE TEBOURBA JEDAIDA COMPLEX IN MANOUBA. LOT 2: CIVIL ENGINEERING WORKS
Project Manager: National Company of Water Exploitation and Distribution (SONEDE) – SONEDE is the only drinking water operator in Tunisia. It is a public company under the supervision of the Ministry of Agriculture
project area: The project area is located in the western suburbs of the capital Tunis.
Consistency of the project:
- Construction of two semi-underground tanks with capacity 1500m3 and 1000m 3
- Construction of two valve chambers
- Construction of a chlorination chamber and a telemetry chamber
- Construction of a pumping station
- Construction of two gardian lodges
- fence construction
Project cost: 2 545 602, 106 Tunisian Dinars (TTC)
Year of completion: Start of work order was given on 15/04/2017
Turnaround time: 18 MONTHS